Last year,
I noted that the Transportation Committee of the City Council had a very, very long stretch without any meetings- and that one important item, the Multi-Modal Transit Center Update, was supposed to happen during that stretch. That was in February. The Transportation Committee met only three times last year, in April, June and September. At the September meeting, the
Transit Center Update was finally received and filed.
Taking a look at the report, there are three options on the table, and three construction possibilities if either of the latter two options are chosen. The three options are:
- No-build. Leave the buses downtown, at the current over-capacity terminal. Obviously, this would be bad.
- Build a new terminal on Vine St. near the Metrolink station, but only route buses that require a layover there. This would mean that routes that flow through downtown would not stop at the terminal, such as 1, 10, 14, and 16, and the network would be severely broken by a lack of connection points. More bad.
- Build a new terminal on Vine St., and route all bus operations there.
You can take a look at the document to see the three location options for the new station. All three would include 14 bus bays for general transit use, two of which are large enough for 60' articulated buses, and 4 bays for long-distance buses. Option 1 would use the site purchased by the City Council for the center, across Vine St. from the station, while options 2 and 3 would re-purpose some of the present parking lot for transit operations. This would get buses closer to trains, but in each case the contractor predicts that a parking garage would be "required." While nothing is final yet, I believe Option 1 is the likely candidate.
So, while the transit center project is moving like molasses, it is still moving.